A drainage project at Sandburg Middle School appears to have solved years of basement flooding at the Elmhurst school.

"We did experience some heavy rains, and we did not have any water come into the building and in the spots where it had been coming in for the last few years," Leo Cassidy, District 205's operations director, told a school board committee, according to Patch. "(We) feel very good about the work that happened."

For years, storms had meant flooding in the school's basement. Work began over the summer, but crews uncovered a related problem that needed to be addressed. District officials decided to let the school year start before resuming construction, Patch reported.

The project included digging a nine-foot hole in front of the school's main entrance and closing the auditorium.

A District 205 summary of the June 23 Board of Education meeting described the drainage work entering its second phase. That phase involved replacing some cracked piping under the auditorium floor, with additional testing planned afterward.

Board President Athena Arvanitis, who has a child at Sandburg, said at a September board meeting that she was disappointed a school-year project would apparently disrupt operations, according to Patch.

The district has also identified storm drain problems at Churchville Middle School. Cassidy said the district better understands what is happening with the pipes there. He said the district feels confident "we're able to knock that out." Repairs are planned for next year.